BREMER RIVER SEWER RISING MAIN REPLACEMENT & PUMP STATION BUILDING RENEWAL
IPSWICH, QLD | URBAN UTILITIES / DOWNER WSP
Contract Value ($3M) | 2025
Allstar Infrastructure was engaged by Downer WSP as part of Urban Utilities' wastewater network upgrade program to deliver critical sewer infrastructure works associated with the Bremer River crossing and pump station renewal. The project involved the construction of new DN355 HDPE sewer rising mains, renewal of the existing pump station building and associated assets, construction of network structures and integration with HDD river crossing works.
The project required complex civil, structural and mechanical works, deep excavations, tie-ins to live sewer infrastructure and coordination between multiple contractors operating within a constrained urban environment.

OUR SCOPE
-
Construction of DN355 HDPE sewer rising main from SPS352 to the western bank of the Bremer River
-
Construction of DN355 HDPE sewer rising main from the eastern bank of the Bremer River connecting to the SP358 common rising main
-
Pump station building renewal works
-
Structural concrete works and associated civil infrastructure
-
Supply and construction of GRV (Gas Release Valve) chamber
-
Deep excavation and trench support systems
-
Tie-ins to existing wastewater infrastructure
-
Coordination with HDD river crossing works
-
Site-wide reinstatement works
-
Testing, commissioning and operational handover
-
QBCC certification and project close-out
CHALLENGES / HIGHLIGHTS
-
Deep excavations for construction of sewer infrastructure and pump station structures requiring engineered trench support systems
-
Coordination with HDD contractors to facilitate installation of the river crossing and interface between trenchless and open-cut construction methodologies
-
Open-cut trench construction leading to designated HDD launch and receival pit locations
-
Renewal of the pump station building, including structural and architectural upgrades to meet current operational and compliance requirements
-
Construction adjacent to live wastewater assets requiring careful planning and sequencing
-
Tie-ins of new rising main infrastructure to existing sewer network assets and HDD-installed pipeline sections
-
Protection and support of existing underground and above-ground services throughout construction activities
-
Management of multiple civil, structural, mechanical and utility interfaces within a constrained work area
-
Completion of comprehensive site reinstatement works following construction
-
Achievement of QBCC certification and compliance sign-off through rigorous quality assurance, testing and documentation processes
-
Safe delivery with minimal disruption to ongoing wastewater network operations
PROJECT OUTCOME
The project successfully delivered critical wastewater infrastructure upgrades, including new sewer rising mains, pump station building renewal works and associated network assets. Through effective planning, contractor coordination and strong quality management processes, Allstar Infrastructure achieved practical completion, QBCC certification and client acceptance while delivering a durable, long-term solution for Urban Utilities' wastewater network.