top of page

Our works

SEWAGE TREATMENT PLANT UPGRADE

UPGRADING AND MAINTAINING CRITICAL WASTEWATER INFRASTRUCTURE

​

VARIOUS SITES, QLD

URBAN UTILITIES (FULTON HOGAN)

$50M ($2M ONGOING) | JULY 2020 – 2023

​

Allstar Infrastructure was engaged by Fulton Hogan to deliver civil, building, and maintenance works as part of the Urban Utilities Northern Treatment Plant Capital Works Program. This program focuses on brownfield treatment plant renewals and upgrades across six major urban and coastal sewage treatment plants, supporting Urban Utilities’ transition from an asset-centric to a customer-centric approach.

SCOPE OF WORK:

​

  • Substation construction – Built new 200-series blockwork substation structures

  • Asbestos removal – Safe removal of old tiles within existing substations

  • Fire door replacement – Removal, installation, and certification of new fire doors and frames, including painting

  • Vegetation and grounds maintenance – Managed grass and plant areas within treatment plants

  • Substation room renovations

    • Wall and floor painting

    • Epoxy floor coating

    • Brickwork on penetrations

    • Supply, installation, and certification of Sika Combiflex products for construction joints

  • Mechanical infrastructure upgrades – Supplied and installed mechanical platforms, stairways, and handrails

allstar-project-sewerage-treatment-plant-upgrade3.jpg
allstar-project-sewerage-treatment-plant-upgrade2.jpg
allstar-project-sewerage-treatment-plant-upgrade1.jpg

CHALLENGES AND SOLUTIONS:

​

  • Works delivered across multiple sites – Required efficient coordination and project management

  • Operating in high-voltage environments – Successfully managed works within substations

  • Ensured minimal disruption to plant operations – Maintained safety and service continuity

​

Allstar Infrastructure continues to play a key role in improving sewage treatment infrastructure, delivering high-quality, safe, and efficient upgrades that support long-term environmental and operational resilience.

allstar-project-sewerage-treatment-plant-upgrade4.jpg
All Star Logo.jpg

Locations

Brisbane

1622 Wynnum Road

Tingalpa  QLD  4173

Gold Coast

12/8 Hopper Avenue

Ormeau QLD 4208

Sunshine Coast

257 Old Gympie Road Narangba QLD 4504

Socials

  • Facebook
  • LinkedIn
bottom of page