IPSWICH SPECIAL SCHOOL RETAINING WALL REPAIR
IPSWICH, QLD | DEPARTMENT OF EDUCATION
CONFIDENTIAL ($XM) | 2025
Allstar Infrastructure was engaged to design and construct a complex retaining wall and associated civil infrastructure upgrades at Ipswich Special School. The project involved the delivery of structural, civil and building works within a live educational environment, requiring careful planning, stakeholder coordination and strict safety controls to minimise disruption to school operations.
The works improved site stability, drainage performance, vehicle access and overall functionality while delivering a durable, long-term infrastructure solution that complied with Department of Education standards and specifications

OUR SCOPE
-
Design and construction of retaining wall
-
Installation of screw pile foundations
-
Construction of 385m² suspended reinforced concrete slab
-
5.5m structural slab span
-
Department of Education specification fencing and gates
-
Brickwork and blockwork construction
-
Existing stormwater infrastructure relocation
-
Driveway expansion works
-
Associated civil, drainage and reinstatement works
CHALLENGES / HIGHLIGHTS
-
Design and construction of a retaining wall utilising screw pile foundation technology suited to variable ground conditions and constrained site access
-
Construction of a suspended concrete slab spanning 5.5m across a 385m² footprint requiring engineered formwork and propping design
-
Delivery of works within an operational school environment while maintaining a safe interface between construction activities, students, staff and visitors
-
Supply and installation of Department of Education compliant gates and fencing meeting security and operational requirements
-
Brickwork and blockwork construction across structural and boundary elements requiring coordination of multiple trades
-
Relocation of existing stormwater infrastructure while maintaining drainage continuity and minimising impacts on surrounding works
-
Driveway expansion works improving vehicle access, circulation and functionality across the school grounds
-
Successful delivery of a complex multi-disciplinary project incorporating structural, civil and building works under a single construction programme
-
Zero Lost Time Injuries (LTI) and strong safety performance throughout project delivery