top of page

Our works

BELMONT SUBSTATION 11HV UPGRADE

ENHANCING ELECTRICAL INFRASTRUCTURE IN A LIVE HV SUBSTATION

​

MANSFIELD, QLD

ZINFRA / POWERLINK

$2M ($800K+) | JULY 2023 – OCTOBER 2023

​

Allstar Infrastructure was engaged by Zinfra and Powerlink to upgrade a local substation, marking our first project within a live high-voltage (HV) substation. This critical upgrade required detailed planning, precision execution, and strict safety compliance.

SCOPE OF WORK:

​

  • Concrete bunded slab and plinth construction – Supporting HV transformer installation

  • Piled concrete footings – Ensuring structural stability

  • Underground services installation – Integrating essential infrastructure

  • Structural steel erection – Delivered within a live HV brownfield environment

energy.jpg

CHALLENGES AND ACHIEVEMENTS:

​

  • Worked within a live HV substation – Ensure strict compliance and safety measures

  • Coordinated staging with maintenance and planned outages – Avoided operational disruptions

  • Managed procurement challenges – Navigated strict material specifications

  • Addressed design delays and changes – Collaborated with the client to mitigate impacts

  • Maintained project schedule – Opened concurrent work fronts to counteract delays

  • Zero incidents or lost-time injuries – Demonstrated strong safety performance

  • Built strong client relationships – Earned a solid reputation through successful delivery

​

Allstar Infrastructure successfully upgraded the Belmont Substation, ensuring enhanced reliability and performance of the local power network.

All Star Logo.jpg

Locations

Brisbane

1622 Wynnum Road

Tingalpa  QLD  4173

Gold Coast

12/8 Hopper Avenue

Ormeau QLD 4208

Sunshine Coast

257 Old Gympie Road Narangba QLD 4504

Socials

  • Facebook
  • LinkedIn
bottom of page