NPARC AC WATER MAINS REPLACEMENT
NORTHERN PENINSULA AREA, QLD | CAPE YORK, QLD | QUEENSLAND GOVERNMENT
CONTRACT VALUE ($5M) | JUN 2025 - APR 2026
Allstar Infrastructure was engaged directly by the Queensland Government to deliver the replacement of ageing asbestos cement (AC) water mains across the Northern Peninsula Area in Far North Queensland.
The project involved the renewal of critical water infrastructure servicing the communities of Bamaga, Injinoo, New Mapoon and Umagico. Working in one of Australia's most remote regions, Allstar coordinated closely with Northern Peninsula Area Regional Council (NPARC), local stakeholders and community representatives throughout project delivery to minimise disruption and maintain essential water services.
OUR SCOPE
-
Removal and replacement of ageing AC water mains
-
Installation of new HDPE water mains
-
Live water main changeovers and commissioning
-
Excavation, trenching and pipe laying works
-
New service connections and network tie-ins
-
Valve, hydrant and fittings installation
-
Testing, commissioning and asset handover
-
Traffic management and public safety controls
-
Road, verge and surface reinstatement works
-
Community and stakeholder engagement
-
Environmental and cultural heritage compliance
-
Principal Contractor responsibilities
CHALLENGES / HIGHLIGHTS
-
Delivery of critical water infrastructure works across multiple remote Cape York communities
-
Extensive planning and coordination of plant, equipment, materials and personnel mobilisation to one of Australia's most remote project locations
-
Management and safe removal of ageing asbestos cement (AC) water mains
-
Maintaining water services to residents through carefully planned shutdowns and network changeovers
-
Working within operational community environments while minimising disruption to residents and local stakeholders
-
Managing wet season risks, remote logistics and supply chain constraints
-
Coordination with Council representatives, community leaders and local stakeholders throughout delivery
-
Delivery of works as Principal Contractor with responsibility for safety, quality, environmental and programme outcomes
-
Implementation of local employment and community engagement initiatives where possible
-
Successful completion of works with strong safety performance and zero major environmental incidents
PROJECT OUTCOME
The project successfully renewed critical water infrastructure across the Northern Peninsula Area, replacing ageing assets with a modern HDPE water network designed to improve reliability and reduce future maintenance requirements. Through strong planning, stakeholder engagement and disciplined project delivery, Allstar Infrastructure safely delivered the works while maintaining essential services and supporting long-term water security for the region's communities.