SUBSTATION BATTERY ENERGY STORAGE SYSTEM (BESS) UPGRADES
DELIVERING CRITICAL ENERGY INFRASTRUCTURE ACROSS REGIONAL NORTH QUEENSLAND
​
REGIONAL AND NORTH QLD
ZINFRA / ERGON ENERGY
$4M PER ANNUM | JUNE 2023 – ONGOING (7-YEAR PROGRAM ACROSS 92 SITES)
​
Allstar Infrastructure was awarded the BESS Program of Works Upgrades, a 7-year project spanning 92 sites in partnership with Zinfra and Ergon Energy. In 2024, we successfully constructed eight new substations across regional North Queensland, including sites in Townsville, Cairns, Kewarra Beach, Mackay, Rockhampton, Mundubbera, Rasmussen, Howard, Emerald, Burnett River, and Gordonvale.
.jpg)
SCOPE OF WORK:
​
-
Bulk earthworks – Cut, fill, and compaction of imported materials
-
Access road construction – Providing durable and all-weather site access
-
Underground services installation
-
Buried conduits and earthing cables
-
In-situ concrete electrical pits and on-ground slabs
-
Battery storage infrastructure
-
Precast concrete plinths for battery units
-
Site drainage and reinstatement
-
Perimeter works – Fencing and asphalting
CHALLENGES AND ACHIEVEMENTS:
​
-
Remote site locations – Required efficient logistics and project coordination
-
Limited local material suppliers – Detailed procurement planning ensured timely delivery
-
No on-site engineering team for design changes – Implemented proactive communication and remote coordination
-
Precast electrical pits manufactured off-site – Reduced on-site construction time
-
Standardised design across multiple sites – Increased efficiency and cost savings
-
Zero incidents or lost-time injuries – Maintained a strong safety record
​
Through detailed planning and innovative construction methods, Allstar Infrastructure continues to enhance energy storage capacity across Queensland, supporting grid stability and sustainable energy solutions.